ANALYSIS OF NEW PRODUCTION LINE PROJECT IMPROVEMENT THROUGH CRITICAL PATH METHOD (CPM), DESIGN STRUCTURE MATRIX (DSM) AND PROGRAM EVALUATION AND REVIEW (PERT)
Abstract
Implementing manufacturing projects involves many parties, using various resources and efforts, and facing difficult or even uncontrolled problems. Those indicate a need for planning tools or methods that can help manage resources effectively, which can help anticipate problems that will arise as soon as possible. There are projects in companies involved in the automotive parts manufacturing industry that perform poorly due to project implementation. Those are due to iterations and restructuring that took place and poor project implementation scheduling. The purpose of this research is to analyze and identify a series of activities and process time to build a new production line using Critical Path Method (CPM), Design Structure Matrix (DSM), and Evaluation and Review Technique (PERT) Program to be able to implement management targets. This study shows an increase in the construction of new production lines with the previous duration, four tears, 13 critical paths from 18 activities. At the same time, after the repair, a total time 185 days is total tears 0, 9 critical lines from 18 activities with a success rate of 90.1%. With this study's results, it recommends that companies with new production line construction projects consider using PERT-CPM techniques in project scheduling
References
Arianie, G. P., & Puspitasari, N. B. (2017). MENINGKATKAN EFISIENSI DAN EFEKTIFITAS SUMBER DAYA PERUSAHAAN ( Studi Kasus : Qiscus Pte Ltd ). 12(3), 189–196.
Badruzzaman, F. H., Fajar, M. Y., Rohaeni, O., Gunawan, G., & Harahap, E. (2020). Cpm and pert technique efficiency model for child veil production. International Journal of Scientific and Technology Research, 9(4), 1470–1476.
Cerezo-Narváez, A., Pastor-Fernández, A., Otero-Mateo, M., & Ballesteros-Pérez, P. (2020). Integration of cost and work breakdown structures in the management of construction projects. In Applied Sciences (Switzerland) (Vol. 10). https://doi.org/10.3390/app10041386
Danilovic, M., & Sandkull, B. (2005). The use of dependence structure matrix and domain mapping matrix in managing uncertainty in multiple project situations. International Journal of Project Management, 23(3), 193–203. https://doi.org/10.1016/j.ijproman.2004.11.001
Dimyati, H., & Nurjaman, K. (2014). Manajemen Proyek : CV Pustaka Setia.
Dister, C. J., Jablonski, A., & Browning, T. R. (2015). Applying dsm methodology to rank risk of internal controls in critical infrastructure enterprises. Modeling and Managing Complex Systems - Proceedings of the 17th International DSM Conference, (Dister 2013), 123–136. https://doi.org/10.3139/9783446447264.012
Driyani, D., Kom, M., Mustari, D., Kom, M., Informatika, T., & Pgri, U. I. (2017). MANAGEMEN PROYEK UNTUK PERANCANGAN APLIKASI PENJUALAN ONLINE BERBASIS WEB. 5(1), 6–12.
Elsye, V., Latief, Y., & Sagita, L. (2018). Development of Work Breakdown Structure ( WBS ) Standard for Producing the Risk Based Structural Work Safety Plan Of Building. 06003.
Fedderick, H., & Gerald, L. (2001). INTRODUCTION TO OPERATIONS RESEARCH. McGraw-Hill Higher Education.
Garold D. Obelrender (2000) Project Management for Engineering and Contruction. Oklahoma State university.
Hamdy, T. A. (2003). Operations Research : An Introduction Book. (Perason Prentice hall).
Heizer Jay. (2015). Operation Management tenth edition. Retrieved from https://drive.google.com/file/d/1CWyPVuEhEVy5dm7ocxo8bBzNWG4_JiRF/view
Hillier, L. (2000). with PERT / CPM. 468–532
Kartika, H., & Setia Bakti, C. (2020). Analysis of 6004-2RSL SKF Bearing Inventory By Economic Order Quantity (EOQ) Method in Spart Part Division. Journal of Industrial Engineering & Management Research, 1(1), 17-27. https://doi.org/10.7777/jiemar.v1i1.19
Kurniawan, E., Gunawan , W., & Syarifudin, A. (2020). ANALISA VIBRASI MAIN SEA WATER PUMP DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS DAN FAILURE MODES AND EFFECT ANALYSIS DI PT KRAKATAU DAYA LISTRIK. Journal of Industrial Engineering & Management Research, 1(2), 238-251. https://doi.org/10.7777/jiemar.v1i2.65
Knoepfel, H., & Berger, R. (n.d.). Project Cost Management. In 5th Edition PMBOK (Ed.), Proj Manage in Prog, Tools and Strategies for the 90s, Int Resour on the Appl of Ideas, Knowl and Exper Concern Proj and Proj (2013th ed.). https://doi.org/10.14445/23488352/ijce-v4i11p101
Levin, R. I., & Kickpatric, A. . (1972). Perentjanaan dan Pengawasan Dengan PERT dan CPM. (Bharatara. Jakarta).
Low Foon Siang, Chong Heap Yih. 2012 A Comparative Approach of Japanese Project Management in Construction, Manufacturing and IT Industries, Universiti Tunku Abdul Rahman. 2012.
Margineanu, L., Prostean, G., & Popa, S. (2015). Conceptual Model of Management in Automotive Projects. Procedia - Social and Behavioral Sciences, 197(February), 1399–1402. https://doi.org/10.1016/j.sbspro.2015.07.085
Nafkha, R. (2016). the Pert Method in Estimating Project Duration. Information Systems in Management, 5(4), 550.
Nur, R., & Suyuti, M. A. (2020). Mini Press Tool as Learning Practical: Designing, Manufacturing, and Analysis. Journal of Industrial Engineering & Management Research, 1(2), 9-14. https://doi.org/10.7777/jiemar.v1i2.34
Ohno T. (1988) Toyota production system beyond large-scale production. Tokyo, Japan: Productivity Press, Kraus Productivity Organization, Ltd..
Piccirillo, I. N., Almeida, L. F. M. de, Araújo, L. Q. de, & Silva, S. L. da. (2017). Design Structure Matrix and Project Management: bibliometric analysis. Product Management & Development, 15(2), 86–91. https://doi.org/10.4322/pmd.2017.008
Purwanto, A. (2020). Design of Food Product Using Quality Function Deployment in Food Industry. Journal of Industrial Engineering & Management Research, 1(1), 1-16. https://doi.org/10.7777/jiemar.v1i1.20
Prayuda, R. Z. (2020). Continuous Improvement Through Kaizen In An Automotive Industry. Journal of Industrial Engineering & Management Research, 1(1), 37-42. https://doi.org/10.7777/jiemar.v1i1.24
Riantini Supriadi, L. S., Biruni, R., & Latief, Y. (2018). Development of work breakdown structure (WBS) dictionary for the construction works of precast concrete bridge. IOP Conference Series: Materials Science and Engineering, 420(1). https://doi.org/10.1088/1757-899X/420/1/012004
S., A. (2018). Improving the Work Breakdown Structure of the Plant Installation - Case: Asphalt Plant. International Journal of Engineering and Management Sciences, 3(5), 174–187. https://doi.org/10.21791/ijems.2018.5.20.
Suwandi, S., & Hari Hadi, A. (2020). Value Analysis Method For Cost Reduction Analysis of Fuel Filter Poducts at PT Duta Nichirindo Pratama. Journal of Industrial Engineering & Management Research, 1(1), 28-36. https://doi.org/10.7777/jiemar.v1i1.22
Soeharto , Iman (1999) " Manajemen proyek jilid 1 : dari konseptual sampai operasional / Iman Soeharto ; editor Yati Sumiharti "
Setia Bakti, C., & Kartika, H. (2020). Analysis of Ice Cream Product Quality Control With Six Sigma Method. Journal of Industrial Engineering & Management Research, 1(1), 63-69. https://doi.org/10.7777/jiemar.v1i1.29
Siswanto. (2007). Operation Research. (Penerbit Erlangga Jakarta).
Supriadi, L. S. R., Wisesatama, B., & Latief, Y. (2018). Development of work breakdown structure (WBS) dictionary for road construction works. IOP Conference Series: Earth and Environmental Science, 195(1). https://doi.org/10.1088/1755-1315/195/1/012007
Subagyo, P., Asri, M., & Handoko, T.H (2013) Dasar-Dasar Operations research, Yogyakarta: BPFE. 2013.
Taketomi T. (2009) Adjusting function and office design in Japanese-style project management organizations - applying the idea of KPM. In: Ohara S, Asada T, editors. Japanese project management KPM - innovation, development and improvement, Singapore: World Scie.
Urbana, A. Y., Eppinger, S. D., & Browning, T. R. (2020). An introduction to modeling and analyzing complex product development processes using the design structure matrix ( DSM ) method Applying the design structure matrix to system decomposition and integration problems : a review and new directions Managing c. 7–8.
Wulfram, I. (2007). Ervianto , Wulfram I . " Manajemen proyek konstruksi / Wulfram I . 658